Large/development sites: - Large Panel System
Sole plates and d.p.c.'s are laid first.
Roofs are then assembled up on the ground using soleplates for setting out. The completed roof is then lifted to one side.
Ground floor large wall panels including whole elevation sections are then erected on the soleplates.
Factory manufactured cassette floor deck/panels are then craned into place (where applicable).
First floor large wall panels including whole elevation sections are then erected on first floor platform.Roofs are then craned back and fixed into position.
Fascias and soffits are then completed.